Timeline
  Neighborhoods | Greens & Parks | Meriam Center | Greenway & Preserve
The planning, environmental review and entitlement phase of Meriam Park has taken approximately 4 years (May 2003 - April 2007).

May 2003
 
Begin Initial Site Studies & Analysis
December 2003
 
Charrette #1: 7-day public design process held in downtown Chico storefront
June 2004
 
Charrette #2: 3-day mini-charrette to plan restoration and enhancement of Little Chico Creek greenway
October 2004
 
Charrette #3: 3-day mini-charrette to plan mixed-use Meriam Center
January 2005
 
File initial applications with City of Chico
July 2005
 
Environmental Review Process begins with Notice of Preparation (NOP) and Initial Study (IS)
April 2006
 
Charrette #4: Mini-charrette for an expansion of Bidwell Presbyterian Church in Meriam Park
November 2006
 
Draft Environmental Impact Report (Draft EIR) released by the City of Chico
March 2007
 
 
Early 2008
 
Begin Phase 1 infrastructure improvements
Mid 2008
 
Begin Phase 1 building construction
Late 2008
 
Initial homes and commercial buildings available for occupancy
 
2018-2020
 
Probable completion of Meriam Park
Print This Page  

 
New Urban Builders

Overview | Planning Process | Review Process | Questions & Comments | What's New | Home
© 2006-2012, New Urban Builders, Inc. | 539 Flume Street #200 | Chico, California 95928 | 530-893-8400